A large emergency binder alone does not keep a business running. Time-critical activities must be known, responsibilities assigned and planned solutions workable.
Standard 200-4 of the German Federal Office for Information Security (BSI) addresses business continuity management (BCM): systematic preparation to maintain and restore essential activities during interruptions. It provides a detailed approach and supporting tools.
A central element is business impact analysis (BIA). It examines how interruption effects change over time and identifies particularly time-critical activities. Understanding their dependencies helps develop suitable continuity solutions.
A small manufacturer dispatches all products from one warehouse. Water damage makes the building inaccessible. During preparation, the business examines how long deliveries could wait and what delays would mean.
An agreed alternative location might help. Before relying on it, establish transport routes, access to stock data, available staff and packaging. An alternative site has prerequisites of its own and can introduce additional dependencies.
Choose a time-critical service and describe a realistic outage. With the affected staff, check available alternatives and remaining gaps.
Assign an owner to resolve open points with management. Keep objectives and next steps manageable. An exercise then provides evidence of whether the planned continuity can be achieved under the assumed conditions.
Information date: 16 October 2026.
For the alternative dispatch location, a short procedure records who makes the decision, which information must be available and how dispatch resumes. Staff walk through the sequence together. The plan is useful when its prerequisites are genuinely available in the intended situation.
An exercise might reveal that packaging is ready but approved access to stock data is missing. That finding leads to a concrete improvement and another check. From plan to exercise explains the next step.